Subject: SUPPORT SITE ANNUAL TRANSFORMER PREVENTATIVE MAINTENANCE

    1. Purpose. Annual preventative maintenance (PM) on electrical substation transformers requires a series of power outages to safely conduct and restore power to the impacted areas.

    2. Applicability. There are two electrical loops that distribute power throughout the Support Site. Loop 1 predominantly feeds the Housing units, while Loop 2 predominantly feeds the non-Housing Facilities. All Housing units and Facilities on the Support Site will be impacted, the phasing of which is outlined in paragraph 3.

    3. Facilities Impacted, Scheduled Dates and Time Frames.

      Monday, November 14, 2011– Loop 2.6 from 0800 to 1430:

      B2089 ( Fitness center/Pool); Villa Capri; Villa Ischia,; Villa Procida; Villa Ventotene; Villa Ponza; Central Park/Amphitheater; Tennis Courts/Skateboard Park.

    Wednesday, November 16, 2011 – Loops 2.2 and 2.1, from 0800 to 1430:

      B2072 Village Forum Central & East, this includes the Chapel, Community Center, Library and Youth Centers); B2071 (Fire Station and nearby Sewer Pump); B2060 (Main Gate Complex); B2088 (Vet Clinic/Kennel) and External Lighting; B2072 (Village Forum West, this includes Bambusa Restaurant, EDIS, Espresso Bar, FFSC, Laundromat, MVRO, Mini-Mart, Navy Lodge, PPSO, Navy Lodge, etc.); B2088 (Thrift Shop Only).

    Friday, November 18, 2011 – Loops 2.3 and 2.5 from 0800 to 1430:

      B2087 (Bachelor Lodge); B2078 (MWR Warehouse and Annex); B2081 (POV); B2077 (AFRTV Studio); B2080 (Security Training Center); B2093 (Back Gate Complex); B2074 (Housing Maintenance Facility); B2075 (Public Works); B2076 (MWR Hobby Shop); B2073 (Housing Welcome Center); B2090 (Bowling Alley); B2092 (NEX Auto port).

    Saturday, November 19, 2011 – Loops 1.0 , 1.6 and 1.7 from 0800 to 2000:

      All Housing Units; B2057 (Elementary School); B2058 (High School); B2059 (School Cafeteria, School LAN); School Bleachers (including Fire Pump Station); 2065 Child Development Center; 2070 Telephone Switch Facility.

    Monday, November 28, 2011 – Loops 2.0 and RCEB, from 0600 to 1230:

      All buildings previously listed as part of Loop 2; B2082 (Hospital); B2086 (Hospital Energy Bldg); B2091 & B2091A (Retail Center, this includes the Commissary, Exchange, ITT, NFCU, NEX Vendors, Food Court, Theater, Post Office, etc.); and B2091B (NEX Energy Bldg).

    Wednesday, November 30, 2011 – Loops 1.4 and 1.11, from 0800 to 2000:

      B2001 (Housing Unit); B2002 (Housing Unit); B2003 (Housing Unit); B2004 (Housing Unit); B2005 (Housing Unit); B2006 (Housing Unit); B2007 (Housing Unit); B2008 (Housing Unit); B2009 (Housing Unit); B2010 (Housing Unit) and B2011 (Housing); B2150 (Housing Unit); B2151 (Housing Unit); B2152 (Housing Unit); B2153 (Housing Unit); B2154 (Housing Unit); B2155 (Housing Unit); B2156 (Housing Unit); B2157 (Housing Unit); B2158 (Housing Unit); B2159 (Housing Unit); B2160 (Housing Unit); B2161 (Housing Unit); B2162 (Housing Unit) and B2163 (Housing Unit).

    Tuesday, December 6, 2011 – Loop 1.3, from 0800 to 2000:

      B2012 (Housing Unit); B2013 (Housing Unit); B2014 (Housing Unit); B2015 (Housing Unit); B2016 (Housing Unit); B2017 (Housing Unit); B2018 (Housing Unit); B2019 (Housing Unit); B2027 (Housing Unit); B2030 (Housing Unit).

    Monday, December 12, 2011 – Loop 1.2, from 0800 to 2000:

      B2020 (Housing Unit); B2022 (Housing Unit); B2024 (Housing Unit); B2025 (Housing Unit); B2026 (Housing Unit); B2032 (Housing Unit); B2033 (Housing Unit); B2034 (Housing Unit) and B2035 (Housing Unit).

    Wednesday, December 14, 2011 – Loop 1.1, from 0800 to 1430:

      B2050 (Housing Unit); B2051 (Housing Unit); B2052 (Housing Unit); B2053 (Housing Unit); B2054 (Housing Unit); B2055 (Housing Unit); B2056 (Housing Unit); B2036 (Housing Unit); B2037 (Housing Unit); B2038 (Housing Unit).

    Friday, December 16, 2011 – Loops 1.5 and 1.8, from 0800 to 1430:

      B2028 (Housing Unit); B2029 (Housing Unit); B2031 (Housing Unit); B2039 (Housing Unit); B2040 (Housing Unit); B2041 (Housing Unit); B2042 (Housing Unit); B2043 (Housing Unit); B2044 (Housing Unit); B2045 (Housing Unit); B2046 (Housing Unit); B2047 (Housing Unit); B2048 (Housing Unit); B2049 (Housing Unit); B2114 (Housing Unit); B2115 (Housing Unit); B2116 (Housing Unit); B2117 (Housing Unit); B2118 (Housing Unit); B2119 (Housing Unit); B2120 (Housing Unit); B2121 (Housing Unit); B2122 (Housing Unit); B2123 (Housing Unit); B2124 (Housing Unit); B2125 (Housing Unit); B2126 (Housing Unit); B2127 (Housing Unit); B2128 (Housing Unit); B2129 (Housing Unit).

    Tuesday, December 20, 2011 – Loops 1.9 and 1.10 from 0800 to 1430:

      B2101 (Housing Unit); B2102 (Housing Unit); B2103 (Housing Unit); B2104 (Housing Unit); B2105 (Housing Unit); B2106 (Housing Unit); B2107 (Housing Unit); B2108 (Housing Unit); B2109 (Housing Unit); B2110 (Housing Unit); B2111 (Housing Unit); B2112 (Housing Unit); B2113 (Housing Unit); B2070 (Telephone Switch Building); B2147 (Housing Unit); B2147A (Housing Unit); B2148 (Housing Unit); B2148A (Housing Unit); B2149 (Housing Unit) and 2149A (Housing Unit); B2130 (Housing Unit); B2131 (Housing Unit); B2132 (Housing Unit); B2133 (Housing Unit); B2134 (Housing Unit); B2135 (Housing Unit); B2136 (Housing Unit); B2137 (Housing Unit); B2138 (Housing Unit); B2139 (Housing Unit) and 2140 (Housing Unit); B2141 (Housing Unit); B2142 (Housing Unit); B2143 (Housing Unit); B2144 (Housing Unit); B2145 (Housing Unit); B2146 (Housing Unit).

    4. Attention Support Site Housing Residents: All Support Site Residents will experience two separate outages. The first outage will occur on Saturday, November 19, 2011 from 0800 to 2000. The second outage will occur on the date your specific building unit is listed above.

    Please be advised that you may experience short fluctuations in power (approximately 10 minutes in length) on days your building is not listed. This is normal, as power must be transferred to properly feed specific substation Loops that are not scheduled for maintenance that day. This applies for outages scheduled on Loop 1 substations only (i.e. Housing residents will not be impacted during outages scheduled for Loop 2 substations).

    5. Fire Systems: Due to battery back-up capability, all Facility and Housing life safety systems will function under normal operating conditions.

    6. Advertising and Notification of Power Outages. Public Works will provide advance notices to Customers through hand given notification sheets, PAO notes, Panorama Staff Reports, Facebook postings and messages displayed on the MWR MARQUEE.

Installation Information

PSC 817 Box 40
FPO AE
Naples, Italy 09622
+39-081-568-5547