NBPL Miramar Fuel Pipeline and Relocation Project

 

Construction Update (as of June 29, 2018)


The Miramar Pipeline Repair project is 98% complete. Approximately five miles of the southern end of the Miramar Fuel Pipeline in the Point Loma area have been replaced to ensure the continued safe and long-term use of the pipeline. This project addressed the pipeline segments that were identified and prioritized for repair or replacement based on the 2008 internal pipeline inspection. Construction activities began in February 2016, and the last segment of new pipeline was commissioned and transporting fuel on March 8, 2018. Construction is expected to be completed July 2018.


Active Construction - Road Striping

  • Rosecrans Street, between Naval Base Point Loma and Talbot Street


Construction activities on Rosecrans Street will occur Saturday, June 30 to replace striping in previously slurry sealed areas.  Construction activities are scheduled  from 7 a.m. to 5 p.m.

During these hours, drivers will be able to travel north and south on Rosecrans Street. Road work will require removing on-street parking on Rosecrans to stripe the bike lanes.

Residents on Rosecrans Street may not be able to access their driveways or garages for 1-2 hours if striping is needed in front of their residence.

Please do not walk, drive, or park on the newly striped road until traffic control is removed. The construction schedule is weather dependent and subject to change. For more up to date information, call the project information line, (844) 409-9846. 

Click here to see the map of the current and upcoming project areas of the pipeline route.  

***For your own safety, please do not enter the construction work zone.***

 

Future Pipeline Projects

The next phase of work on Miramar Pipeline will commence in June 2018. The Anomaly Repairs project will repair 31 anomalies such as dents, corrosion, and metal loss at multiple locations at Marine Corps Air Station Miramar, Tecolote Canyon, and in the communities of Clairemont, Morena, and Midway District. The scope of the upcoming project is based on findings of the 2013 internal pipeline inspection. In December 2017, preliminary site investigations and surveys were completed. Properties directly affected by Anomaly Repair work will receive a construction notice in advance. Click here to see the Anomaly Repairs Notice.

A future project, currently under consideration, may relocate part(s) of Miramar Pipeline located in the Clairemont community of San Diego due to the encroachment of non-Navy developments within the existing Miramar Pipeline easement. Encroaching development diminishes the Navy’s ability to access the pipeline for regular inspection, routine maintenance and emergency response.

The ongoing work on Miramar Pipeline will enhance the overall operational safety, reliability and integrity of the pipeline in support of our nation’s military readiness.

 

Recently Completed Work

La Playa Restoration 

In summer 2017, the Navy removed invasive plants and returned native plants to areas of the La Playa waterfront, a scenic recreational area for the local Point Loma community. Restoration efforts were part of the Miramar Pipeline Repair and Relocation project which relocated about 5 miles of the southern end of the Miramar Pipeline into the City of San Diego right-of-way. After approximately 1,100 feet of pipeline were removed from the waterfront, those project areas were restored.

Through a multi-agency collaboration between the Navy, Port of San Diego, Army Corps of Engineers, and community stakeholders the restoration was strategically designed to reintroduce diverse native flora, stabilize eroded banks, maintain the natural beauty of the waterfront, and ensure recreational access.

The restoration areas are closed as the new plants are becoming established. Neighbor support is
needed to keep the plants healthy and the slopes stable for the long-term success of the restoration project. Please:

• Stay out of the restoration areas
• Keep pets on leash
• Do not let pets deposit waste in the restoration areas
• Use only designated paths
• Do not cut or damage the fence

To report damaging pet activities, call:
County of San Diego Department of Animal Services

619-767-2675

To report vandalism or other unlawful activity, call:
Harbor Police (Dispatch)

619-686-6272

The restoration fence and on-grade irrigation system with its associated solar panels will be removed when the plants are established or the restoration areas no longer need protection. Ultimately, restoration efforts on the La Playa waterfront will reduce invasive plant species and provide long-term stability to the banks by reintroducing native plant species appropriate for the environment.

A variety of native plants were selected to enhance the existing wetland plants and to provide much needed stability. The varied planting palette provides layers of vegetation and varying root systems that together provide ground and surface erosion control for slopes. Once established, native plants are low maintenance and do not need to be watered. The majority of the fully grown native plants are expected to be 3 to 4 feet in height.

La Playa Restoration Plants
The various native species planted include:
- Saltgrass (Distichlis spicata)
- Alkali heath (Frankenia salina)
- Pickleweed (Salicornia sp.)
- Western marsh-rosemary (Limonium californicum)
- Coast sagebrush (Artemisia californica)
- Coyote brush (Baccharis pilularis)
- Coast sunflower (Encelia californica)
- Common tarweed (Deinandra fasciculata)
- California buckwheat (Eriogonum fasciculatum) 

To see the Winter 2018 La Playa construction notice, click here

Contact Us
The Navy has a project email address and information phone line for inquiries. Updates will also be posted here on the project website, and on Twitter and Facebook.

 

 

Share This Page

This is an Official US Navy Website
Switch to Full Site
Switch to Mobile Site